ATC Spindle Safety Commissioning Guide

11kW BT40 water-cooled ATC spindle motor ATC safety commissioning reference
Direct answer: Commission an ATC spindle with rotation locked out, clean dry air, the correct holder and pull stud, verified clamp/unclamp feedback, and a low-speed tool-change test before automatic production.

Safe commissioning sequence

  1. Inspect mechanical and pneumatic connections.
  2. Verify the approved air range for the exact model.
  3. Test unclamp and return without a cutting tool.
  4. Install the correct holder and pull stud.
  5. Verify clamp confirmation, no-tool/home, and emergency-stop logic.
  6. Run a low-speed tool-change cycle and record alarms and sensor states.